How long does an enforcing agency have to grant or deny building permits under Act 230?

Prepare for the Michigan Hydronic and Process Piping Test. Utilize flashcards and multiple choice questions with answers and explanations. Ensure your success on the exam with our comprehensive study resources!

Under Act 230, an enforcing agency is required to grant or deny building permits within a specified timeframe to ensure efficiency and accountability in the permitting process. The correct answer, which indicates a period of 10 business days, aligns with the legislative intent to expedite construction projects while giving enforcing agencies adequate time to review applications thoroughly.

This 10-day period allows for necessary due diligence in assessing the permit applications against safety, zoning, and building standards, providing a balance between regulatory oversight and the need for timely responses to applicants who are eager to start their projects. By setting this timeframe, the act promotes clarity and predictability for builders and developers, which is vital for planning and financing construction activities.

Understanding this timeline is crucial for professionals in the construction and architectural fields as it impacts project scheduling and management.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy